In year 2015; have completed the solar FIT project.
overall cost RM64,214.
as of now per day estimated 30-40 return on sunny day.
record down and shall review after 21 years if profitable.
Issue
28 Apr 2016 - after almost 4 month waiting no income, call TNB renewable energy department to check status only figure out FITCD not yet obtain from SEDA.
30 Apr 2016 - SEDA status update to completed project, but raise another question which need contractor to update. Status change to Query project. still got few step till FITCD.
2 May 2016 - FITCD not yet obtain, TNB cannot release payment
10 May 2016 - FITCD obtain after so many month.
14 May 2016 - enquiry TNB for 1st payment, take about 30 days payment term after invoice.
14 Jun 2016 - 1st payment received.
23 Jun 2016 - 2nd Payment received.
Summary
Shall not keep waiting, with no confirmation.(need to know the hold process avoid wasting time waiting)
shall check with TNB or contractor once payment yet received.
done FITCD in SEDA.
TNB 1st payment received.
hope everythings smooth, no issue on the coming years(Pray).